A Resolution authorizing the Director of Purchasing to Process a Change Order to the Agreement with Performance Construction & Engineering, LLC for the S. Broadway Ave Sewer Separation - Hazel Ave to North Ave Contract in the amount of $90,000.00.
Legistar status: PassedPurchasing and deliveryNeighborhood changes
Where it stands
- Sunday, April 19, 2026 · Introduced
- Monday, April 27, 2026 · Infrastructure and Technology Committee: recommended for approval · result recorded: Pass
- Tuesday, May 5, 2026 · Committee of the Whole: (PLACED ON CONSENT AGENDA)
- Tuesday, May 12, 2026 · City Council: approved on the Consent Agenda
| Legistar status | Passed |
|---|---|
| Legistar passage date | Tuesday, May 12, 2026 |
| Enactment number and date (as Legistar labels them) | R26-131 · Tuesday, May 12, 2026 |
When it takes effect
The published text checked contains no sentence stating when this takes effect. Check the final document.
From the published memo
“Authorize additional funds for the completion of the sewer separation project begun in 2025 which is to be completed in spring of 2026.”