A Resolution authorizing the execution of a Joint Funding Agreement with the State of Illinois, the execution of a Phase 3 Construction Engineering Services Agreement with BLA, Inc. in the not to exceed amount of $461,138.00, and the appropriation of $1,561,138.00 for the Galena-New York Resurfacing Project.
Legistar status: PassedPublic moneyPurchasing and delivery
Where it stands
- Thursday, June 4, 2026 · Introduced
- Monday, September 21, 2026 · Infrastructure and Technology Committee: recommended for approval · result recorded: Pass
- Tuesday, October 6, 2026 · Committee of the Whole: (PLACED ON CONSENT AGENDA)
- Tuesday, October 13, 2026 · City Council: approved on the Consent Agenda
| Legistar status | Passed |
|---|---|
| Legistar passage date | Tuesday, October 13, 2026 |
| Enactment number and date (as Legistar labels them) | R26-247 · Tuesday, October 13, 2026 |
When it takes effect
The published text checked contains no sentence stating when this takes effect. Check the final document.
From the published memo
“To execute the Joint Funding Agreement for State-Let Construction Work there by reserving sufficient funds to cover the local agency share of the project cost by resolution and to approve the Phase 3 Construction Engineering Services Agreement with BLA, Inc.”